Client:Hoover Elementary School
Date:November 05, 2012

Hoover Elementary School

This renovation project was completed while the building was unoccupied in 44 days from June to August. The renovation portions of the work consisted of complete exterior paint and seal, interior paint, replacement of flooring, and complete removal and replacement of the existing ceiling system through the school. The building’s plumbing, heating and electrical systems and controls were all upgraded. Replacement of the exterior architectural metal siding gave the building a new, updated look. Since the mechanical, electrical, flooring, painting and ceiling work took place in every room in the school, BGCI took measures to enhance communications between subcontractors to ensure that performance expectations were aligned and the critical project completion date was met.